Crow Metals, Romford
Granulator Installation
A new 185mm 4core SWA supply was required to a copper granulator at Crow Metals. UK Power Network involvement was required on this project, as our load monitoring test proved the existing supply was not sufficient for the new granulator.
TNS organised and liaised with UKPN and Siemens on the behalf of Crow Metals, to create a hassle free project. The new granulator required additional control and safety wiring, as the machine was not factory fitted with emergency stop buttons.
Works comprised of:
- Third party management (UPKN + Siemens)
- Distribution equipment
- Control wiring and safety management
- Containment
- Main supply wiring