Tottenham Hale Train Station Lighting and EV Charging Installation

Tottenham Hale station, Ferry Lane, Tottenham, Greater London. N17 9NA
Project Overview: Tottenham Hale Train Station Lighting and EV Charging Installation

TNS was tasked with the installation of electrical infrastructure upgrades at Tottenham Hale Train Station. This included the installation of 4 new lighting columns, using Abacus raise-and-lower circular flange-plated systems, designed to provide presence illuminance and absence dimming in compliance with industry standards

In addition 2 EO Genius 2 EV chargers were installed, seamlessly integrated with NCP’s management system to enable smooth operation for users. The project also required load monitoring to confirm available capacity, and the installation of a new sub-main supply along the length of the platform, using existing containment systems, with work completed out-of-hours (OOH) to minimise disruption.

A new GRP feeder pillar was also installed, housing the new distribution equipment required to power the upgrades. The project involved RITA form applications to ensure all compliance and regulatory standards were met.

Scope of Works:

– Installation of 4 Abacus raise-and-lower lighting columns with presence illuminance and absence dimming

– Installation of 2 EO Genius 2 EV chargers, integrated with NCP systems

– Load monitoring to ensure electrical capacity

– Installation of a new sub-main supply along the platform in existing containment (OOH)

– Installation of a new GRP feeder pillar with distribution equipment

– Completion of RITA form applications for compliance